![]() |
|||||||||||
|
|||||||||||
|
May 10, 2001: Contours refined, track progresses, detention pond gains definition
[for enlarged view- 85k, but worth the wait] December 15: macadam goes down to underlay the track.
Early November saw the curbing completed on the track
October brought a change in the colors, and speedy work on the curbing on the track.
Below: The Summer rains hamstrung work on the fields, but as late August arrived the outlines of the
photo September 1, 2000 [This photo looks in the opposite direction from the panorama below]
|
|
photo November '99
Clearing of trees for the new fields was halted until the judge's order lifted the temporary restraining order. On the left, in the background, are the existing field and structure, looking to the west. Swinging to the right follows the line of Prospect Avenue, and looks to the north at the right edge of the photograph. Seton Hall Prep gets approval for fields 11/19/99 By Dawn S. Onley Staff Writer, A Superior Court judge yesterday allowed Seton Hall Preparatory School to continue building athletic fields on a Prospect Avenue tract that West Orange residents were fighting to keep open space. Judge Arthur Minuskin issued a temporary restraining order last week prohibiting any further work on the $1.4 million project until both sides could be heard on the issue. Residents filed the emergency motion to protect the area, where wildlife and century-old trees abound on 44 wooded acres. The school owns the land and said the athletic fields and track, which will take up seven to 10 acres, are desperately needed. At yesterday's hearing, Michael Saffer, attorney for the residents, argued the school failed to comply with a township
ordinance that required it to submit an environmental impact statement to the planning board. The statement, Saffer said, would show the project's environmental effects and also would allow residents to be heard.
''The plain language of the ordinance says all preliminary and final site plan applications of 5 acres or more shall be
accompanied by an environmental impact statement," Saffer said. "It doesn't say may be or should be; it says 'shall.' "
John Murray, attorney for Seton Hall Preparatory School, and Sal Anderton, who represents the West Orange Planning Board, countered that the project had already met full compliance with the planning board. Both said the school had
hired four experts to testify on the environmental impact of the project over a series of hearings and the planning board ultimately found the project to be acceptable.
Furthermore, Murray and Anderton added that any environmental concerns should have been addressed long before the planning board signed off on the project on July 22.
''It's 110 days since this action was approved by the planning board," said Murray. "This application is untimely and even
if you get over that hurdle, we believe we have fully complied on all issues and the planning board so found."
The judge agreed. ''I originally was of the opinion that submission of the (environmental statement) was a jurisdictional
requirement, but apparently it's not," Judge Minuskin said, adding that the West Orange township law appeared to be flexible, allowing expert testimony in the place of a formal environmental impact statement. |
| [Spiritual] [Academics] [Guidance] [Activities] [Athletics] [Calendar] [Gallery] |